Purchase file
Audit-ready packet · ready for CPSR sample · 82% complete
Step 07 · Purchase file
ADS-24-017-PF-001
Patriot Components LLC — M83513-04-G connectors (Qty 480) · auto-assembled by Anbu, ready for final approvals.
File completeness
82%
6 of 9 items complete · 2 missing · 1 pending
Two supplier-provided documents (ISO certificate + traceability letter) and one Procurement Manager approval block PO release. All competition, price-reasonableness, and flowdown evidence is in the packet.
Approval routing
- MCApproved
Maya Chen
Buyer (originator)
- DMPending
David Morales
Procurement Manager
- EGPending
Elena Garcia
Supplier Quality
Packet contents
Source recommendation memo
CompleteAuto-generated; supplier rationale, price analysis, conditions
RFQ log
Complete3 RFQs issued (Patriot, Eagle, Redstone); 3 responses received
Quote comparison
CompleteSide-by-side: unit price, lead time, compliance, risk
Supplier eligibility checklist
CompleteSAM check + CAGE verification + AVL status confirmed
Price reasonableness memo
CompleteVariance vs. baseline + 3-quote competition documented
Flowdown clause checklist
CompleteDFARS 252.246-7007 + FAR 52.244-6 + ISO 9001 confirmed
Updated Patriot ISO 9001 certificate
MissingRequested in RFQ; supplier response pending
Traceability letter
MissingOEM authorized distribution letter required for electronic components
Procurement Manager approval
PendingRequired: selected supplier not lowest quote ($1,104 above Eagle)
Source recommendation memo (auto-generated)
CompleteMemorandum · ADS-24-017-PF-001 · ADS-24-017
Source recommendation: Patriot Components LLC
Anbu recommends Patriot Components LLC for M83513-04-G (Qty 480, MIL-DTL-83513 Micro-D Connector) in support of Subcontract ADS-24-017.
Patriot's quote of $42.10/unit ($20,208 extended) is 4.6% above Eagle Supply ($39.80) and 13.0% above Redstone Electronics ($37.25). Patriot is recommended despite higher unit price because Eagle's 35-day lead time exceeds the June 18 milestone (driven by Mod 0001's accelerated July 1 delivery), and Redstone has an unresolved traceability gap from PO-2281 that disqualifies them under DFARS 252.246-7007 (counterfeit electronic part detection).
Patriot's 12-PO history with Apex shows 92% on-time delivery and one resolved NCR. Selection is conditional on receipt of an updated ISO 9001 certificate (current expires in 45 days) and an OEM traceability letter, both requested in RFQ-001. Procurement Manager approval is required because the selected supplier is not the lowest-priced quote.
Audit trail
Every routing decision, exclusion, and recommendation is explainable — what Anbu did, when, and why.
Detected Modification 0001 in contract package
2026-04-29 09:14Quantity 100 → 120; first delivery July 15 → July 1; funded value $620K → $780K; new First Article Test deliverable.
Actor: Anbu
Re-prioritized BOM by Mod 0001 critical path
2026-04-29 09:14Long-lead items (PCB, connectors, regulator, capacitors) flagged for immediate sourcing.
Actor: Anbu
Indexed 47 vendor email threads + 38 historical POs
2026-04-29 09:15Built relationship signal per supplier: response time, on-time delivery, quality events, prior parts supplied.
Actor: Anbu
Held Redstone Electronics from RFQ batch
2026-04-29 09:15Reason: PO-2281 had unresolved traceability gap and SAM status needs re-verification. Routed to Elena Garcia (Supplier Quality).
Actor: Anbu
Held MilSpec Finishers from RFQ batch
2026-04-29 09:15Reason: New supplier; quality review pending before initial RFQ inclusion. Routed to Elena Garcia (Supplier Quality).
Actor: Anbu
Drafted 5 supplier-specific RFQs with embedded flowdowns
2026-04-29 09:16DFARS 252.246-7007, FAR 52.244-6, ISO 9001/AS9100 attached per supplier capability.
Actor: Anbu
Embedded ISO cert renewal request in Patriot RFQ
2026-04-29 09:16Trigger: March 20 email from Sarah Mills indicated cert expires within 45 days.
Actor: Anbu
Approved RFQ batch ADS-24-017-B1 for send
2026-04-29 11:42All 5 RFQ drafts reviewed and released to suppliers.
Actor: Maya Chen
Parsed 3 supplier quotes for connector RFQ-001
2026-04-30 16:08Patriot $42.10 / Eagle $39.80 / Redstone $37.25. Compliance, lead time, and origin normalized.
Actor: Anbu
Recommended Patriot Components despite +5.8% over lowest
2026-04-30 16:08Rationale: Eagle 35-day lead time misses June 18; Redstone traceability gap unresolved. Routed to David Morales (Procurement Manager) for approval.
Actor: Anbu
Next actions
Await Patriot ISO cert response
RFQ asked for updated cert in supplier reply
Await OEM traceability letter
Required per DFARS 252.246-7007
Route to David Morales for approval
Procurement Manager (selected supplier ≠ lowest)