Contract intelligence
Anbu read the full package and pulled the procurement-relevant signal
Step 02 · Contract intelligence
Ruggedized Power Control Unit Kits
Subcontract ADS-24-017 · Northstar Tactical Vehicles, Inc. → Apex Defense · End customer: U.S. Army
Contract value
$1,240,000
Authorized total
Funded value
$780,000
Up from $620,000 after Mod 0001
First delivery
July 1, 2026
Was July 15, 2026 (accelerated)
Procurement actions generated
9
From Mod 0001 + BOM (120 kits)
Funding guardrail
Total contract value
$1,240,000
Funded value (Mod 0001)
$780,000
Procurement commitments queued
$312,400
Approval required before total commitments exceed $780,000 funded ceiling.
Modification 0001 — what changed
Anbu summary
Modification 0001 increased quantity from 100 to 120 kits, accelerated first delivery to July 1, 2026, and added a First Article Test Summary Report due June 24, 2026.
Procurement impact: Long-lead electronic components and machined enclosures must be sourced immediately to protect the July 1 delivery milestone.
Quantity
Funded value
First delivery milestone
New deliverable
Delivery schedule
July 1, 2026
30 kitsAccelerated by Mod 0001
August 30, 2026
30 kitsOctober 15, 2026
30 kitsNovember 15, 2026
30 kitsRisk alerts
4 openFirst delivery accelerated by 14 days
Original July 15 → Mod 0001 sets July 1, 2026 for 30 kits. Long-lead PCBs and connectors are now critical-path.
Funded value below total contract value
$780,000 funded against $1,240,000 total. Anbu will flag any sourcing action that pushes committed spend above funded value before written authorization.
New deliverable: First Article Test Report
First Article Test Summary Report required by June 24, 2026. Test article components must arrive earlier than first production lot.
Counterfeit-parts traceability required
Contract Section 7 requires traceability documentation for critical electronic components.
Flowdown requirements detected
Treated as detected requirements; counsel reviews final clauses on PO. Will be embedded in every supplier RFQ.